Wednesday, July 23, 2025

Case Study: Implementing Project Management Tool for ApexBuild Construction Inc.

 This example illustrates how a construction company leverages a project management tool to manage projects through subprojects and tasks, assign teams, track time and budgets, and manage equipment.

Company Overview

ApexBuild Construction Inc. is a mid-sized general contracting company specializing in commercial and residential projects. Projects range from single-house builds to multi-story office complexes. The company adopts a digital transformation initiative by integrating a project management tool tailored to their operations.


Project Overview: Midtown Commercial Complex

1. Project Structure

The Midtown Commercial Complex is a large-scale construction project broken down hierarchically:

  • Main Project: Midtown Commercial Complex

    • Subproject A: Foundation and Earthworks

      • Mini Project A1: Excavation

      • Mini Project A2: Foundation Pouring

    • Subproject B: Structural Framework

      • Mini Project B1: Steel Structure Installation

      • Mini Project B2: Concrete Slabs

    • Subproject C: Electrical and Plumbing

      • Mini Project C1: Underground Plumbing

      • Mini Project C2: Electrical Conduits

    • Subproject D: Finishing Works

      • Mini Project D1: Interior Painting

      • Mini Project D2: Flooring

Each Mini Project contains multiple Tasks, which are the smallest work unit.


2. Team Management and Role Assignment

Each Mini Project has a team assigned, selected via the tool’s Team Assignment Module, which includes:

Team for Mini Project A1: Excavation

  • Team Lead: John Reyes – Oversees work progress and coordinates with the project manager.

  • Excavator Operator: Marco Santos – Operates heavy equipment.

  • Site Engineer: Liza Dela Cruz – Ensures specifications and quality standards are met.

  • Laborers (3): Assist in manual tasks, measurement, and on-ground support.

Defined Responsibilities (in the tool):

  • Team Lead: Report daily progress, escalate issues.

  • Operator: Operate machinery according to plan.

  • Engineer: Conduct inspections, submit compliance reports.

  • Laborers: Execute manual excavation, support operator.


3. Equipment Allocation

Through the Equipment Management Feature, the following resources are assigned:

  • Excavator (CAT 320D) – Assigned to Marco Santos

  • Laser Level Tool – Assigned to Liza Dela Cruz

  • Shovels, Picks, Wheelbarrows – Assigned to laborers

  • Safety Equipment (PPE) – Assigned to all team members


4. Task Assignment and Scheduling

Each team is assigned tasks within the mini-project. Example for Mini Project A1 – Excavation:

Task IDTask DescriptionAssigned ToBudgeted TimeDeadlineStatus
T-A1-01Mark excavation areaSite Engineer4 hoursDay 1In Progress
T-A1-02Excavate to depth 1.5mOperator + Laborers24 hoursDay 3Not Started
T-A1-03Check levelsSite Engineer3 hoursDay 3Not Started
T-A1-04Move excavated soilLaborers12 hoursDay 3Not Started

Each task entry in the tool includes:
  • Time Tracking: Each worker logs daily hours on the task.

  • Budgeted Time Comparison: Tool highlights overruns or delays.

  • Dependency Mapping: For example, Task T-A1-02 cannot begin until T-A1-01 is completed.


5. Time and Budget Tracking

Daily Reporting

  • Every team member logs in via the mobile app.

  • Reports time spent per task.

  • Notes issues (e.g., weather delay).

Budget vs. Actual Analysis

  • For Task T-A1-02:

    • Budgeted Time: 24 hours

    • Time Spent After 2 Days: 20 hours

    • Estimated Completion: 28 hours → Overrun alert generated

Tool flags the task and notifies the Project Manager and Team Lead for review and adjustment.


6. Real-Time Dashboard Features

The management tool includes:

  • Gantt Chart View: Shows subprojects and mini-project timelines

  • Daily Activity Feed: Summarizes time spent, status updates

  • Equipment Usage Reports: Tracks usage hours, idle time

  • Personnel Allocation Summary: Who is assigned where

  • Budget Utilization Graphs: Actual vs. Planned time and cost


7. Results and Benefits

After using the project management tool for 6 months:

MetricBefore ToolAfter Tool
Project Completion Timeliness78% on-time            92% on-time
Equipment Idle Time30%                    12%
Task Delay DetectionManual & Late            Real-time
Labor EfficiencyModerate            High due to task clarity
Communication GapsFrequent            Minimal via task-linked chats

Conclusion

By implementing a structured project management system with subprojects, team management, task assignments, and real-time tracking, ApexBuild significantly improved project visibility, team coordination, and efficiency. The granularity of control (from project > subproject > mini project > task) helped isolate problems early and allocate resources effectively.

No comments:

Post a Comment

๐Ÿง  Basic ReactJS Programming Language Tutorial: Getting Started with Modern Web Development

 ReactJS is one of the most popular JavaScript libraries for building modern, interactive user interfaces — especially for single-page appli...